AETERNA provided full-scope QA/QC management services during the construction of a major gas processing facility. Our team established and implemented quality control procedures covering welding, NDT, civil/structural, mechanical, piping, electrical, and instrumentation disciplines.
2,500+ welds across piping, structural, and equipment
Complete MDR with ITPs, weld maps, and NDT reports
98.6% weld acceptance rate on first inspection
The project involved multiple construction contractors and simultaneous work fronts, requiring coordinated quality oversight. Tight schedule demanded efficient inspection planning without compromising quality.
We deployed a dedicated QA/QC team including certified welding inspectors, CSWIP/ASNT NDT technicians, and discipline-specific inspectors. Our team managed all quality documentation including ITPs, weld maps, NDT reports, and MDR compilation. We conducted regular quality audits and facilitated joint inspections.
Developed project-specific ITPs, inspection checklists, and weld maps
Discipline-specific inspectors performing hold-point witnessing and NDT coordination
Complete MDR with weld maps, NDT reports, material certificates, and QA close-out
Measurable outcomes delivered through our technical expertise and commitment to quality.